You are a risk manager on a construction project. The project sponsor requests a report on the top five risks by exposure. You have calculated the risk exposure for each risk as the product of probability and impact. Which document should you consult to obtain the most current probability and impact values for each risk?
The risk register is the primary document that contains detailed information about each identified risk, including its probability, impact, risk score, and response plan. It is regularly updated throughout the project lifecycle, so it holds the most current values. To report on top risks by exposure, you must consult the risk register for the latest probability and impact assessments. This ensures that the report reflects the current risk landscape and supports informed decision-making.
Why this answer
The risk register is the centralized repository for all risk-related information, including current probability and impact assessments. It is updated throughout the project, making it the authoritative source for calculating risk exposure. Other documents like the risk management plan, issue log, and lessons learned register serve different purposes and do not contain the real-time risk data needed for this report.
Exam trap
The trap here is confusing the risk management plan with the risk register; the plan describes the process, while the register contains the actual risk data.