PMI-RMP Risk Process Facilitation Practice Question
A project manager is conducting a risk review. During the meeting, a new risk is identified. What should be done immediately?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Assess the new risk's probability and impact
New risks must be captured in the risk register and evaluated for impact and probability.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Assess the new risk's probability and impact
Why this is correct
Once a risk is identified, it must be analyzed to determine if it requires a response.
- ✗
Wait until the next scheduled risk review cycle
Why it's wrong here
Risks should be addressed as soon as they are identified to prevent escalation.
- ✗
Add it to the issues log
Why it's wrong here
Risks are future events; the issues log is for current problems.
- ✗
Assign a risk owner immediately
Why it's wrong here
Assessment must happen before assignment to understand the resource requirement.
- ✗
Update the risk management plan
Why it's wrong here
The management plan is a process document, not a repository for individual risks.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.