PfMP Portfolio Risk Management Practice Question
Which document is used to track the status of approved risk responses?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Portfolio Risk Register.
The Portfolio Risk Register tracks the status and progress of identified risks and their responses.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Portfolio Charter.
Why it's wrong here
The charter authorizes the portfolio.
- ✓
Portfolio Risk Register.
Why this is correct
This is the primary tool for tracking risks and responses.
- ✗
Portfolio Roadmap.
Why it's wrong here
The roadmap tracks timelines and milestones.
- ✗
Resource Management Plan.
Why it's wrong here
This plan covers resource usage, not risk responses.
About these practice questions
Courseiva writes every PfMP question from scratch — 199 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PfMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PfMP exam.