Predictive Plan-Based Methodologies
easy
A project manager is creating the project schedule. The team estimates that the optimistic time for an activity is 10 days, the pessimistic time is 30 days, and the most likely time is 15 days. Using PERT three-point estimation, what is the expected duration?