MB-910 Describe Dynamics 365 Field Service Practice Question
Exhibit
Refer to the exhibit.
{
"ResourceSchedule": {
"ResourceId": "RES-101",
"StartTime": "2026-03-20T08:00:00Z",
"EndTime": "2026-03-20T17:00:00Z",
"WorkHours": [
{"Day": "Monday", "Start": "09:00", "End": "17:00"},
{"Day": "Tuesday", "Start": "09:00", "End": "17:00"},
{"Day": "Wednesday", "Start": "09:00", "End": "17:00"},
{"Day": "Thursday", "Start": "09:00", "End": "17:00"},
{"Day": "Friday", "Start": "09:00", "End": "17:00"}
],
"TimeOff": [
{"Start": "2026-03-22T00:00:00Z", "End": "2026-03-24T00:00:00Z"}
]
}
}Refer to the exhibit. Resource RES-101 has a work schedule with time off from March 22 to March 24. Today is March 20 (Friday). A dispatcher tries to schedule a 2-hour work order on March 23 (Monday) at 10:00 AM. What will happen?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The work order cannot be scheduled because the resource is on time off.
The work order cannot be scheduled because the resource is on time off. Resource RES-101 has time off from March 22 to March 24, and March 23 falls within that period, making the resource unavailable. Option A is incorrect because the technician's agreement does not override scheduled time off. Option B is incorrect because although March 23 is a workday, the time-off exception takes precedence. Option D is incorrect because the system will not schedule the work order at all due to the time-off conflict; it will not create a schedule with a conflict flag.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The work order will be scheduled if the technician agrees.
Why it's wrong here
Incorrect: The system prevents scheduling during time off.
- ✗
The work order will be scheduled because March 23 is a workday.
Why it's wrong here
Incorrect: Time off overrides work hours.
- ✓
The work order cannot be scheduled because the resource is on time off.
Why this is correct
Correct: Time off blocks availability.
- ✗
The work order will be scheduled but the system will flag a conflict.
Why it's wrong here
Incorrect: The system respects time off and will not schedule.
Go deeper
Related to this question
About these practice questions
One of 941 original MB-910 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This MB-910 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-910 exam.