Courseiva
Security Operations and AdministrationmediumMultiple ChoiceObjective-mapped

Change Management Rollback: What to Do After a Failed Change Implementation

During a change management process, the Change Advisory Board (CAB) has approved a change to update a critical database server. After implementation, a rollback is necessary due to unforeseen performance issues. What should the change manager do next?

Quick Answer

Executing the rollback plan and then scheduling a post-implementation review is the correct response because the rollback plan was already built into the original change request and approved by the CAB as part of that same package; it's a pre-authorized contingency, not a new action that requires fresh approval before it can be used. When unforeseen performance issues appear after implementation, the priority is restoring service stability as quickly as possible, and executing a plan that's already been reviewed and approved is the fastest safe path to that outcome, since re-submitting a new change request for the rollback itself would introduce delay while the problem is actively affecting the system. Once stability is restored, scheduling a post-implementation review captures what went wrong, why the pre-implementation testing didn't catch the issue, and what should change about the process going forward, closing the loop and feeding lessons learned back into future change planning, which is a core part of ITIL-aligned change management. Treating rollback as something that needs a brand-new approval cycle would misunderstand how contingency planning works within change management: the contingency is decided in advance precisely so it can be executed without delay when needed. When a question describes a failed change with a pre-approved rollback plan, look for the answer that executes that plan immediately and follows up with a review, rather than one that seeks new approval first.

⚠ Common exam trap

The trap here is that candidates mistakenly think any rollback requires a new change request, but the rollback plan is already part of the approved change, so immediate execution is permitted without further CAB approval.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Execute the rollback plan and schedule a post-implementation review

The change was already approved by the CAB, and the rollback plan is a pre-approved contingency within the original change request. Executing the rollback immediately restores service stability, and scheduling a post-implementation review (PIR) captures lessons learned and ensures compliance with the change management policy. This aligns with ITIL best practices, where rollback is part of the implementation plan and does not require a new change request.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Execute the rollback plan and schedule a post-implementation review

    Why this is correct

    Executing the pre-approved rollback plan is the correct immediate action, followed by a post-implementation review to learn from the failure.

  • Leave the server in its current state and escalate to the CAB for a decision

    Why it's wrong here

    Waiting could cause further issues; the rollback plan is designed to restore the system quickly.

  • Patch the server with the latest updates to resolve the performance issue

    Why it's wrong here

    Applying patches is a separate change and not part of the rollback plan; it may not resolve the performance issue caused by the change.

  • Submit a new change request for the rollback and await CAB approval

    Why it's wrong here

    The rollback plan was already approved as part of the original change request; no new approval is needed for the rollback itself.

About these practice questions

This SSCP question is part of Courseiva's 920-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on SSCP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. After a patch is deployed to a critical server, the system becomes unstable. The change management plan includes a rollback procedure. What should be done FIRST?

hard
  • A.Create a new change request for the rollback
  • B.Conduct a post-implementation review
  • C.Execute the rollback procedure
  • D.Notify the Change Advisory Board

Why C: When a patch deployment causes system instability, the immediate priority is to restore service stability by executing the pre-approved rollback procedure. The change management plan already includes this procedure, so no new approvals are needed; acting quickly minimizes downtime and risk.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This SSCP practice question is part of Courseiva's free ISC2 certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSCP exam.