Courseiva
hardMultiple ChoiceObjective-mapped

CRISC Practice Question: During a risk assessment of a legacy system, the…

During a risk assessment of a legacy system, the assessor finds that no control is currently in place. The inherent risk level is 'critical'. The residual risk will be:

⚠ Common exam trap

Watch out — candidates often assume residual risk is always lower than inherent risk, forgetting that without any controls, residual risk equals inherent risk by definition.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Critical

Residual risk is the level of risk remaining after controls are applied. Since the scenario explicitly states that no control is currently in place, the residual risk remains identical to the inherent risk level, which is 'critical'. Therefore, the residual risk is also critical.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Medium

    Why it's wrong here

    Medium would require some controls.

  • Critical

    Why this is correct

    No controls mean residual risk remains critical.

  • High

    Why it's wrong here

    Inherent risk is critical, not high.

  • Low

    Why it's wrong here

    Low would require strong controls.

About these practice questions

Courseiva writes every CRISC question from scratch — 983 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.