An organization uses a qualitative risk assessment and assigns a likelihood of '3' and impact of '4' on a 5-point scale. The heat map defines risk scores 12-25 as high. What is the risk rating?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

High

Risk score = 3 × 4 = 12, which falls in the high range (12-25).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Critical

    Why it's wrong here

    Critical typically requires a higher score, e.g., 20-25.

  • Medium

    Why it's wrong here

    Medium would be lower, e.g., 6-11.

  • Low

    Why it's wrong here

    Low would be 1-5.

  • High

    Why this is correct

    Score 12 is within the high range.

About these practice questions

This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.