Courseiva
IT Risk IdentificationhardMultiple ChoiceObjective-mapped

CRISC IT Risk Identification Practice Question

An organization has a risk appetite statement that says 'We accept up to $5 million in operational losses per year.' However, a new cloud migration project is estimated to have a potential operational loss of $8 million if a critical failure occurs. The risk capacity of the organization is $20 million. What should the risk practitioner recommend?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement risk treatment measures to reduce the potential loss to below $5 million

The risk tolerance threshold ($5 million) is exceeded by the potential loss ($8 million). The risk appetite is the amount of risk the organization is willing to accept, and this scenario exceeds it. While the risk capacity is higher, the appetite is not met, so risk treatment is needed to bring the residual risk within the tolerance.

About these practice questions

This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.