Courseiva

CISA Practice Question: Information Systems Acquisition, Development, and Implementation

Which of the following is a key control during the deployment phase of a system development life cycle?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Rollback plan

The deployment phase should include a rollback plan to revert to the previous state if the new system fails. This is a critical control to minimize downtime and data loss.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Rollback plan

    Why this is correct

    A rollback plan is essential during deployment to ensure the ability to revert if issues arise.

  • Code review

    Why it's wrong here

    Code review is a development phase control.

  • Threat modeling

    Why it's wrong here

    Threat modeling is typically performed during the design phase.

  • User acceptance testing (UAT)

    Why it's wrong here

    UAT is conducted before deployment, during the testing phase.

About these practice questions

This CISA question is part of Courseiva's 995-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.