During the planning phase of an IS audit, which of the following is the PRIMARY purpose of conducting a risk assessment?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To identify high-risk areas for audit focus

A risk assessment identifies high-risk areas to prioritize audit efforts and allocate resources effectively.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To determine the audit budget

    Why it's wrong here

    Budget is a resource constraint, not the primary purpose of risk assessment.

  • To obtain management approval

    Why it's wrong here

    Approval is an administrative step, not the purpose of risk assessment.

  • To select the audit team members

    Why it's wrong here

    Team selection is based on skills and availability, not directly on risk assessment.

  • To identify high-risk areas for audit focus

    Why this is correct

    Risk assessment drives audit scope and resource allocation.

About these practice questions

This CISA question is part of Courseiva's 995-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.