During a review of the patch management process, the IS auditor finds that critical security patches are applied within 30 days, but the policy requires application within 7 days. The IT manager argues that the delay is due to testing requirements. What should the auditor recommend?

⚠ Common exam trap

CISA often tests the distinction between the auditor's role and management's role, so the trap is choosing escalation or policy relaxation when the correct answer is to require formal risk acceptance by the business owner, preserving auditor independence and the control baseline.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Require risk acceptance documentation for each patch that misses the SLA

The policy requires 7-day patching but actual practice is 30 days, creating a documented control gap. Rather than silently accepting the deviation or weakening the standard, the auditor should recommend that each missed SLA be formally documented as a risk acceptance so management owns the residual risk. This preserves the control baseline while providing an auditable trail of conscious risk decisions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Escalate to senior management immediately

    Why it's wrong here

    Escalation bypasses the auditor's first duty: verify whether testing genuinely requires 30 days and whether the 7-day policy is achievable. Raising to senior management suits repeated, unaddressed non-compliance after remediation attempts; here the finding is fresh and the manager's testing claim is untested, so a recommendation precedes escalation.

  • ✗

    Update the policy to allow 30 days for critical patches

    Why it's wrong here

    Lowering the threshold to 30 days codifies the existing control gap rather than closing it, leaving critical vulnerabilities exploitable for three extra weeks. Policy revision suits environments where vendor testing genuinely cannot compress the window, but here the auditor's mandate is to enforce the 7-day requirement, not legitimise the deviation.

  • ✓

    Require risk acceptance documentation for each patch that misses the SLA

    Why this is correct

    Where testing causes patches to breach the seven-day SLA, documented risk acceptance transfers accountability to business owners for the residual exposure during the delay. This satisfies the stem's compliance gap by ensuring deviations are formally acknowledged rather than silently tolerated, without abandoning the testing control.

  • ✗

    Accept the delay as necessary for stability

    Why it's wrong here

    Accepting the delay treats an unverified claim as justification, leaving the 7-day control unevidenced and critical exposures open for 23 extra days. Tolerating slippage fits low-risk, non-exploitable patches where compensating controls exist; here the policy mandates 7 days and the testing rationale must be validated, not assumed.

About these practice questions

This CISA question is part of Courseiva's 934-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official ISACA exam blueprint

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.