Courseiva

CISA Practice Question: Information Systems Operations and Business Resilience

An organization has implemented a business continuity plan (BCP) and disaster recovery plan (DRP). During a recent full interruption test, the IT team discovered that the recovery time objective (RTO) for a critical application was not met. What is the MOST likely reason for this failure?

⚠ Common exam trap

A common mix-up: candidates confuse RTO with RPO or assume procedural gaps (like missing a tabletop exercise) are the root cause, when the actual failure is a technical capacity limitation at the alternate site.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The alternate site did not have adequate processing capacity to handle the workload.

The most likely reason the RTO was not met is that the alternate site lacked sufficient processing capacity to handle the workload. RTO measures the time to restore service availability; if the failover site cannot support the required compute, memory, or I/O throughput, restoration will be delayed or fail outright. This is a common capacity planning failure in DR testing, where the alternate site is sized for minimal operations but not for the full production load.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The recovery point objective (RPO) was set too low, causing data loss.

    Why it's wrong here

    RPO relates to data loss, not the time to recover (RTO).

  • The backup data was not encrypted, leading to corruption during restoration.

    Why it's wrong here

    Encryption does not typically cause delays; corruption could, but it is less common than capacity issues.

  • The tabletop exercise was not conducted before the full interruption test.

    Why it's wrong here

    While tabletop exercises are valuable, their absence does not directly cause RTO failure; the root cause is typically technical or procedural.

  • The alternate site did not have adequate processing capacity to handle the workload.

    Why this is correct

    Insufficient capacity at the alternate site directly impacts recovery time and is a frequent finding in full interruption tests.

About these practice questions

One of 995 original CISA practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.