Courseiva
mediumMultiple Choice

CISA Practice Question: An IT steering committee is reviewing a proposed…

An IT steering committee is reviewing a proposed project to migrate critical applications to the cloud. Which of the following is the PRIMARY role of the IT steering committee in this decision?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To ensure the project aligns with business strategy

The IT steering committee ensures that IT investments align with business strategy. They are responsible for strategic alignment and approving major projects based on business value.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To perform the technical feasibility study

    Why it's wrong here

    Technical feasibility studies are performed by engineering and architecture teams, who report findings to the committee. The steering committee's primary role is governance: prioritising the project against strategic objectives, approving funding and overseeing risk, not conducting hands-on technical assessment.

  • ✗

    To select the cloud service provider

    Why it's wrong here

    Provider selection is a procurement and technical evaluation activity performed by specialists against requirements, not the steering committee's governance remit. The committee authorises the project and its direction; it does not run vendor evaluations. It is tempting because the committee approves the resulting contract spend, but the actual selection decision belongs to the procurement team.

  • ✓

    To ensure the project aligns with business strategy

    Why this is correct

    The steering committee's primary function is governance: confirming that proposed investments align with and advance the organisation's business strategy. Cloud migration decisions are prioritised on strategic fit, not technical detail, so alignment with business strategy is its core responsibility.

  • ✗

    To manage the project budget and schedule

    Why it's wrong here

    Budget and schedule management is delegated to the project manager, not the steering committee. The committee's remit is strategic direction, prioritisation and go/no-go authorisation. It is tempting because steering committees do approve funding envelopes, but day-to-day financial and scheduling control sits with the project manager under the project board's tolerances.

About these practice questions

Courseiva writes every CISA question from scratch — 934 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva