CISA Practice Question: An IT balanced scorecard for a retail company…

An IT balanced scorecard for a retail company shows that the percentage of IT projects delivered on time has decreased from 85% to 70%. Which perspective of the balanced scorecard is MOST directly affected?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Internal Process

The internal process perspective focuses on operational efficiency and project delivery metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Learning and Growth

    Why it's wrong here

    Learning and growth covers staff competence, training and innovation capacity, not project delivery timeliness. It is tempting because skills shortages can cause delays, and it would be correct if the metric concerned certification rates, training completion or employee capability development.

  • ✗

    Financial

    Why it's wrong here

    The financial perspective covers IT cost, budget variance and value contribution, not delivery schedule performance. It is tempting because late projects often incur cost overruns, so a financial link appears plausible, and it would be correct if the metric concerned IT spend against budget or cost per transaction.

  • ✗

    Customer

    Why it's wrong here

    The customer perspective measures service quality, satisfaction and delivery to business users, not internal project schedule adherence. It is tempting because late delivery can eventually degrade user experience, and it would be correct if the metric were customer satisfaction scores or service availability affecting end users.

  • ✓

    Internal Process

    Why this is correct

    Internal Process covers operational efficiency and delivery capability, so a fall in on-time project delivery directly measures this perspective. The stem's constraint is the 85% to 70% decline in timely delivery, an execution metric, not a customer, financial or learning-and-growth outcome.

About these practice questions

Courseiva writes every CISA question from scratch — 934 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.