Courseiva

CISA Practice Question: Information Systems Acquisition, Development, and Implementation

An IS auditor is reviewing an agile software development project. Which of the following is the most important control to assess?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Sprint review

In agile, the sprint review provides an opportunity to demonstrate completed work and obtain stakeholder feedback, acting as a key control for quality and acceptance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Sprint review

    Why this is correct

    Correct. The sprint review is a control point where stakeholders validate delivered functionality.

  • Daily standup meetings

    Why it's wrong here

    Standups are for coordination, not control.

  • Retrospective

    Why it's wrong here

    Retrospectives focus on process improvement, not acceptance.

  • Product backlog

    Why it's wrong here

    The backlog is a prioritization tool, not a control.

About these practice questions

Courseiva writes every CISA question from scratch — 995 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.