Courseiva

CISA Practice Question: Information Systems Acquisition, Development, and Implementation

An IS auditor is reviewing an agile software development project. Which of the following would be the BEST evidence that adequate controls are in place for user acceptance?

⚠ Common exam trap

CISA often tests the confusion between the sprint review (product acceptance with stakeholders) and the sprint retrospective (internal process improvement), causing candidates to select the retrospective as evidence of user acceptance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Each sprint concludes with a sprint review attended by stakeholders

In agile development, the sprint review is the ceremony where the team demonstrates the completed increment to stakeholders, who provide feedback and formally accept or reject the work. This stakeholder participation at the end of each sprint is the strongest evidence that user acceptance controls are functioning, because acceptance is continuous rather than deferred to a single end-of-project event. It directly addresses the risk that delivered functionality diverges from business needs.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The product backlog is managed by the product owner

    Why it's wrong here

    Backlog management by the product owner evidences requirement prioritisation, not user acceptance testing or sign-off. It tempts because the product owner does own acceptance criteria, but the auditor needs records of users validating the delivered increment against those criteria.

  • ✗

    Daily standup meetings are held to track progress

    Why it's wrong here

    Standups track development progress and impediments, not user validation of increments, so they provide no acceptance evidence. They are tempting because they are a core agile practice demonstrating active project oversight, and would be the correct evidence when auditing progress monitoring or impediment management controls.

  • ✗

    Retrospectives are conducted after each sprint

    Why it's wrong here

    Retrospectives review team process, not whether users validated the delivered increments, so they evidence no acceptance control. They are tempting because they are a genuine agile ceremony that examines the sprint, and would be relevant evidence when auditing team improvement or process maturity rather than user acceptance.

  • ✓

    Each sprint concludes with a sprint review attended by stakeholders

    Why this is correct

    Sprint reviews provide evidence that stakeholders inspect the increment each sprint, satisfying the need for continuous user acceptance in agile delivery. Unlike a single end-of-project sign-off, this recurring stakeholder validation demonstrates acceptance controls operate throughout development, directly addressing the stem's requirement for adequate user acceptance evidence.

About these practice questions

This CISA question is part of Courseiva's 934-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official ISACA exam blueprint

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.