Courseiva
mediumMultiple Choice

CISA Practice Question: An IS auditor is reviewing a system development…

An IS auditor is reviewing a system development project to assess whether it is on schedule. Which of the following would provide the BEST evidence of project progress against the planned timeline?

⚠ Common exam trap

Many candidates confuse evidence of technical progress (like passing unit tests) with evidence of schedule progress, failing to recognize that technical success does not equate to on-time delivery.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Updated project schedule with actual completion dates for milestones

The updated project schedule with actual completion dates for milestones (Option D) provides direct, objective evidence of progress against the planned timeline. It shows the baseline plan, the actual dates work was completed, and the variance, allowing the IS auditor to quantitatively assess schedule adherence. This is the primary artifact for schedule tracking in system development projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Minutes from status review meetings

    Why it's wrong here

    Meeting minutes record discussion and attendance, not verified milestone completion against planned dates. They suit evidencing governance and issue escalation. Schedule assessment requires comparing actual milestone completion dates with the baseline project plan, which minutes may misreport.

  • ✗

    Approved requirements document

    Why it's wrong here

    An approved requirements document evidences scope definition and sign-off, not progress against planned dates. It is the correct artefact when verifying that requirements were captured and authorised. Schedule assessment requires comparing actual milestone completion dates with the baseline project plan.

  • ✗

    Successful unit test results

    Why it's wrong here

    Unit test results evidence code quality and completion of coding tasks, not elapsed progress against planned dates. They are the right evidence when assessing whether modules function correctly. Schedule assessment requires comparing actual milestone completion dates with the baseline project plan.

  • ✓

    Updated project schedule with actual completion dates for milestones

    Why this is correct

    A schedule showing planned milestones alongside actual completion dates lets the auditor compare baseline against reality and compute slippage directly. It is objective, verifiable evidence of timeline performance, unlike verbal updates or forecasts that merely restate intentions.

About these practice questions

Courseiva writes every CISA question from scratch — 934 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.