Courseiva
easyMultiple ChoiceObjective-mapped

CISA Practice Question: A mid-sized company is upgrading its legacy…

A mid-sized company is upgrading its legacy financial system to a new cloud-based ERP. The project manager has decided to use a big-bang cutover approach to minimize costs and time. During the first week post-go-live, users report that several critical reports are generating incorrect totals. An initial investigation reveals that the data mapping from the old system to the new system was not fully validated. Which of the following should the IS auditor recommend as the most appropriate corrective action?

⚠ Common exam trap

Many exam-takers choose Option D (revert to legacy) because it seems safest, but the CISA exam emphasizes cost-effective, risk-based corrective actions that validate data integrity without abandoning the project, making parallel operations the preferred approach.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform a data mapping review and remediation, then run parallel operations until accuracy is confirmed

A big-bang cutover with unvalidated data mapping introduces a high risk of data integrity issues, as seen with the incorrect report totals. Running parallel operations after a data mapping review and remediation allows the IS auditor to validate that the new ERP processes data correctly by comparing outputs with the legacy system, ensuring accuracy before full reliance. This aligns with ISACA's guidance on post-implementation verification and control testing for data conversion in cloud-based ERP migrations.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Perform a data mapping review and remediation, then run parallel operations until accuracy is confirmed

    Why this is correct

    This directly fixes the data mapping issue and validates correctness before relying solely on the new system.

  • Implement additional manual controls and have users double-check all reports

    Why it's wrong here

    Manual controls are error-prone and not sustainable; they do not fix the mapping errors.

  • Increase the project budget and hire more consultants to fix the issues

    Why it's wrong here

    More resources without a clear plan does not guarantee resolution and may mask the real issue.

  • Immediately revert to the legacy system and restart the project with a phased approach

    Why it's wrong here

    Reverting is extreme and may not be feasible; it also wastes the investment made so far.

About these practice questions

This CISA question is part of Courseiva's 995-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.