Courseiva
hardMultiple ChoiceObjective-mapped

CISA Practice Question: A government agency is developing a case…

A government agency is developing a case management system for law enforcement. The project follows an agile approach, releasing iterations every two weeks. During a sprint demo, users discover that the system does not redact personally identifiable information (PII) in documents shared with external parties, violating privacy laws. The development team says they planned to add redaction in a future sprint. The product owner wants to prioritize PII redaction immediately. The project manager is concerned that this will disrupt the release schedule. The IS auditor is assessing the project's risk management. Which of the following is the BEST recommendation?

⚠ Common exam trap

Test-takers frequently confuse risk acceptance (Option D) with a valid agile practice, but the IS auditor must prioritize compliance over schedule, and deferring a legal violation is not acceptable risk management when a feasible mitigation exists.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Re-estimate the sprint and include PII redaction as a top priority, adjusting the schedule accordingly.

It aligns with agile risk management principles: when a critical compliance vulnerability (PII exposure) is discovered, the highest-priority user story must be re-estimated and inserted into the current sprint backlog, even if it means adjusting the release schedule. The IS auditor’s focus is on ensuring that the risk is actively mitigated, not deferred, and re-prioritization is the standard agile response to newly identified high-severity risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement network-level restrictions to prevent external sharing.

    Why it's wrong here

    Addresses symptom but not the root cause.

  • Provide users with training on manual redaction as a workaround.

    Why it's wrong here

    Not a sustainable control.

  • Re-estimate the sprint and include PII redaction as a top priority, adjusting the schedule accordingly.

    Why this is correct

    Balances compliance and schedule.

  • Document the risk and accept the compliance exposure until the planned sprint.

    Why it's wrong here

    Compliance criticality requires immediate action.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

About these practice questions

This CISA question is part of Courseiva's 995-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISA practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISA exam.