An enterprise is adopting a 'Risk-Based Approach' to IT governance. How should this impact the IT budget allocation?
A risk-based approach directs governance funding toward the exposures posing the greatest potential loss, so budget is prioritised for the highest-risk areas. This satisfies the stem's allocation question by tying spend to risk magnitude rather than equal distribution.
Why this answer
A risk-based approach to IT governance directs resources toward the areas of greatest potential loss or impact. Since budget is a finite governance lever, allocating it to the highest risk exposures ensures that mitigation spending is proportional to the likelihood and business impact of each risk. This aligns IT investment with enterprise risk appetite and maximizes the return on every dollar spent on controls.
Exam trap
CGEIT often tests the misconception that risk-based governance means spending more on the oldest or most technically outdated systems, when it actually means spending in proportion to business risk exposure.
How to eliminate wrong answers
Option A is wrong because focusing entirely on legacy system upgrades is a technology-refresh decision, not a risk-prioritized allocation — some legacy systems may carry low risk while newer cloud or third-party services carry higher exposure. Option B is wrong because minimizing budget across the board ignores risk entirely and can increase residual risk by starving high-exposure areas of necessary controls. Option D is wrong because equal distribution assumes every IT department carries identical risk, which contradicts the fundamental premise of risk-based governance that risk is unevenly distributed.