DAF Foundations OF Agile Practice Question
What is the role of the 'Definition of Done' (DoD) in an agile project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To create a clear, shared understanding of what constitutes a completed work item
The DoD provides a shared understanding of quality and completeness for an increment.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To replace the need for project manager oversight
Why it's wrong here
It helps manage quality but does not remove the need for management.
- ✓
To create a clear, shared understanding of what constitutes a completed work item
Why this is correct
This prevents ambiguity about whether work is truly finished.
- ✗
To tell the team how long a task should take
Why it's wrong here
DoD defines quality, not duration.
- ✗
To act as a contract for external vendors
Why it's wrong here
It is an internal team quality standard.
About these practice questions
This DAF question is part of Courseiva's 211-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This DAF practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the DAF exam.