A team is working on a project with high technical uncertainty. Which approach should they adopt?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Adopt an iterative approach with frequent spikes to learn

High uncertainty requires experimentation and 'spike' solutions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Follow the original plan strictly to reduce risk

    Why it's wrong here

    Sticking to a plan in high uncertainty is a high-risk strategy.

  • Adopt an iterative approach with frequent spikes to learn

    Why this is correct

    Spikes allow for research and risk reduction before full implementation.

  • Outsource the uncertain parts of the project

    Why it's wrong here

    Outsourcing doesn't resolve the underlying uncertainty.

  • Delay the uncertain work until the end of the project

    Why it's wrong here

    Delaying high-risk work makes it harder to fix later.

About these practice questions

One of 211 original DAF practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This DAF practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the DAF exam.