Courseiva
Container OrchestrationmediumDrag & DropObjective-mapped

KCNA Container Orchestration Practice Question

Drag and drop the steps for a rolling update of a Kubernetes Deployment into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1. Change the image, 2. Apply the change, 3. Monitor the rollout, 4. Verify the health, 5. Rollback if issues

Change the image, apply, monitor rollout, verify health, and rollback if issues arise.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1. Change the image, 2. Apply the change, 3. Monitor the rollout, 4. Verify the health, 5. Rollback if issues

    Why this is correct

    This order follows the expected workflow: first update the deployment configuration, then apply it, monitor the rollout status, verify the health of new pods, and finally rollback if any issues are detected.

  • 1. Change the image, 2. Monitor the rollout, 3. Apply the change, 4. Verify the health, 5. Rollback if issues

    Why it's wrong here

    Monitoring the rollout before applying the change is meaningless because the rollout hasn't started yet. The change must be applied first to trigger the update.

  • 1. Apply the change, 2. Change the image, 3. Monitor the rollout, 4. Verify the health, 5. Rollback if issues

    Why it's wrong here

    Applying the change before modifying the image is incorrect because there is no actual update to apply. The image change defines what the update should be.

  • 1. Change the image, 2. Apply the change, 3. Verify the health, 4. Monitor the rollout, 5. Rollback if issues

    Why it's wrong here

    Verifying health before monitoring the rollout is premature. The rollout process may still be ongoing; health checks should only occur after the rollout has completed or stabilized.

Go deeper

Related to this question

About these practice questions

One of 833 original KCNA practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This KCNA practice question is part of Courseiva's free CNCF certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the KCNA exam.