CCNA Processes Questions

14 of 89 questions · Page 2/2 · Processes topic · Answers revealed

76
MCQmedium

A Project Manager is implementing Managing Product Delivery. A Team Manager discovers that a specialist product cannot be delivered within the agreed Work Package cost tolerance. What should the Team Manager do?

A.Escalate directly to the Project Board
B.Submit an Exception Report to the Project Manager
C.Absorb the cost by cutting quality criteria without telling anyone
D.Pause the whole project until funds are secured
AnswerB

The Team Manager must notify the Project Manager via an Exception Report when a Work Package tolerance is forecast to be exceeded.

Why this answer

When a Work Package forecast exceeds its tolerance, the Team Manager must immediately raise an Exception Report to the Project Manager.

77
MCQhard

A project is in the Managing a Stage Boundary (SB) process. The Project Manager has identified that the next stage requires specialized external resources that were not accounted for in the outline Business Case. What should the Project Manager do?

A.Update the Business Case and present the revised costs and justification to the Project Board at the stage boundary.
B.Cancel the project immediately without preparing an End Stage Report.
C.Reduce the quality criteria of all upcoming products to offset the cost of the external resources.
D.Procure the external resources immediately using project contingency funds without informing the board.
AnswerA

Stage boundaries are the precise control point to review updated costs and business justification before proceeding.

Why this answer

In SB, if significant changes emerge that affect costs or viability, the Project Manager must update the Business Case and highlight the variances to the Project Board in the End Stage Report / stage boundary submission so the Board can make an informed decision.

78
MCQmedium

During the Managing Product Delivery process, a Team Manager has completed a specialist product. Before handing it over to the Project Manager, what quality check must the product pass according to PRINCE2?

A.Approval from Corporate, Program Management or the Customer
B.formal review by Project Assurance
C.Verification against its Product Description quality criteria
D.Authorization of the next Stage Plan by the Project Board
AnswerC

Products must meet the quality criteria specified in their Product Description and gain the necessary quality sign-off.

Why this answer

Products must be checked against their Product Description quality criteria and signed off by the authority defined in the Product Description.

79
MCQhard

During the Closing a Project process, the Project Manager must prepare a Follow-on Action Recommendations log. Who is the primary audience responsible for acting upon these recommendations after the project is closed?

A.Corporate, Program Management, or operational management
B.Team Managers
C.The Project Manager
D.The Project Board
AnswerA

Corporate or program management and operational line management take ownership of follow-on actions and post-project benefits reviews.

Why this answer

Follow-on action recommendations contain uncompleted or post-project issues, maintenance, and benefits reviews, which are passed to corporate or program management and operational line management.

80
Multi-Selectmedium

A Project Manager is preparing to execute the Managing a Stage Boundary process. Which TWO of the following activities are core parts of this process?

Select 2 answers
A.Producing the End Stage Report
B.Formally handing over project products to corporate operations
C.Creating the detailed Work Package descriptions
D.Appointing the initial Project Board and Executive
E.Preparing the next Stage Plan
AnswersA, E

The End Stage Report is a mandatory output created during Managing a Stage Boundary to summarize stage performance.

Why this answer

Managing a Stage Boundary includes producing an End Stage Report, updating the Business Case, and creating the next Stage Plan.

81
MCQhard

During the Managing Product Delivery (MP) process, a Team Manager has completed a Work Package. What specific action must the Team Manager take before handing the completed products back to the Project Manager?

A.Draft the End Stage Report for the Project Board.
B.Update the Project Business Case with actual costs incurred during manufacturing.
C.Perform a formal project-level post-project benefit review.
D.Check that the products meet their quality criteria and obtain approval records from quality checkers.
AnswerD

The 'Accepting a work package' and 'Executing a work package' activities require checking products against quality criteria before 'Returning a work package'.

Why this answer

In MP, when products are completed, the Team Manager must verify that they meet the quality criteria defined in the Work Package Description and obtain approval/sign-off from the designated authority before delivery.

82
MCQmedium

During the Managing a Stage Boundary (SB) process, the Project Manager needs to update the Business Case. Why is this update necessary at a stage boundary?

A.To replace the Project Initiation Documentation entirely.
B.To verify that the project remains viable and worthwhile before the Project Board authorizes the next stage.
C.To obtain approval from Corporate/Programme management to close the project.
D.To calculate the final bonus for the Project Manager based on completed work.
AnswerB

Updating the Business Case confirms continued business justification prior to stage authorization.

Why this answer

At each stage boundary, the Business Case must be updated with actual costs, actual progress, and revised forecasts to ensure the project remains viable and justifiable before committing resources to the next stage.

83
MCQeasy

During which PRINCE2 process are the Project Management Plan, Risk Management Approach, and Business Case fully developed and baselined?

A.Managing Product Delivery
B.Starting up a Project
C.Initiating a Project
D.Controlling a Stage
AnswerC

IP creates the baseline Project Management Documentation (PID) and its constituent management approaches.

Why this answer

Initiating a Project is the process where all management approaches, baselines, and the comprehensive Project Management Plan are created.

84
MCQhard

A project is currently executing the Controlling a Stage (CS) process. The Project Manager notices that cumulative actual costs are tracking significantly below budget while progress is on schedule. What should the Project Manager do?

A.Automatically initiate the Closing a Project process early.
B.Secretly reallocate the surplus funds to personal bonuses without informing anyone.
C.Ignore the underspend since being under budget never requires management attention.
D.Report the variance in the next Highlight Report and assess if it impacts stage tolerances or forecasts.
AnswerD

All significant variances (positive or negative) must be captured and reported to the Project Board.

Why this answer

Under CS, unexpected variances (including underspend) should be logged as issues or risks and reported to the Project Board via Highlight Reports so the financial forecast can be adjusted if needed.

85
MCQeasy

A project is nearing the end of its current stage. The Project Manager initiates the Managing a Stage Boundary process. What is the primary reason for performing this process rather than continuing straight into the next delivery stage?

A.To allow the Project Manager to take an extended leave while the Board reviews the project
B.To hand over day-to-day management to the Team Managers
C.To rewrite the entire Project Initiation Documentation from scratch
D.To allow the Project Board to review stage performance, assess continued business justification, and authorize the next stage plan
AnswerD

Stage boundaries provide decision gates for the Project Board to evaluate project viability and approve subsequent stages.

Why this answer

Managing a Stage Boundary gives the Project Board a control point to review stage performance, update the business case, and authorize the next stage.

86
MCQmedium

During the Directing a Project process, the Project Board is evaluating whether to authorize the next stage. A minor tolerance deviation occurred in the current stage, but it was successfully managed. Where should the Project Board check to confirm that the business case remains viable despite this deviation?

A.Updated Business Case
B.End Stage Report
C.Daily Log
D.Project Brief
AnswerA

The Project Board reviews the updated Business Case (submitted with the End Stage Report) to confirm continued viability.

Why this answer

The updated Business Case is reviewed by the Project Board during Managing a Stage Boundary and Directing a Project to ensure the project remains viable.

87
Multi-Selecteasy

Which TWO of the following are primary objectives of the Initiating a Project (IP) process?

Select 2 answers
A.Create the Project Management Plan and its subsidiary strategies
B.Disband the Project Board permanently
C.Hand over all project products to the operational environment
D.Appoint the initial Executive prior to project mandate receipt
E.Establish the project's business justification via the Business Case
AnswersA, E

The PMP and management approaches are established in IP.

Why this answer

Initiating a Project aims to understand what needs to be delivered (Project Product Description), establish business justification, and create the Project Management Plan.

88
MCQhard

A Project Manager is executing the Initiating a Project process and is assembling the Project Initiation Documentation (PID). Which of the following components must be newly created or baselined specifically for the PID rather than inherited from the Project Brief?

A.Executive role description
B.Project objectives
C.Project Plan
D.Project Approach
AnswerC

The detailed Project Plan is developed during Initiating a Project to replace the high-level outline found in the Project Brief.

Why this answer

While many elements are refined from the Project Brief, the Project Plan must be fully developed for the PID, providing the detailed schedule and budget for the project stages.

89
MCQhard

During Directing a Project, the Project Board receives an Exception Report from the Project Manager indicating that stage tolerances will be exceeded due to a supplier bankruptcy. What is the correct sequence of actions for the Project Board?

A.Instruct the Project Manager to create an Exception Plan, evaluate it, and then authorize or reject it.
B.Authorize the replacement supplier immediately and update the Stage Plan themselves.
C.Delegate the decision to the Team Manager responsible for the failed supplier.
D.Close the project immediately without requesting further analysis.
AnswerA

The Project Board evaluates the Exception Report, requests an Exception Plan, and then reviews and decides whether to authorize that plan.

Why this answer

Upon receiving an Exception Report, the Project Board must first decide whether to reject or accept the exception, then if accepted, instruct the creation of an Exception Plan, and subsequently authorize it.

← PreviousPage 2 of 2 · 89 questions total