1
Multi-Selectmedium

A Project Manager in the Controlling a Stage process receives a request for change from a stakeholder. Which TWO actions must the Project Manager take first in handling this request?

Select 2 answers
A.Assess the impact of the change on the Business Case, risks, and tolerances
B.Immediately implement the change to satisfy the stakeholder
C.Send the change directly to the Project Board for automatic approval
D.Discard the change if it comes from anyone other than the Executive
E.Capture and log the request in the Issue Register
AnswersA, E

The Project Manager must analyze the impact of the request on scope, time, cost, risk, and business case viability.

Why this answer

When a request for change is received, the Project Manager must capture and record it in the Issue Register, and then assess its impact on the project objectives and tolerances.

2
Multi-Selecthard

During the Managing Product Delivery process, a Team Manager interacts with the Project Manager. Which THREE of the following are responsibilities of the Team Manager within this process?

Select 3 answers
A.Delivering completed products and reporting progress via Checkpoint Reports
B.Approving the overall Project Initiation Documentation
C.Creating Team Plans to schedule specialist activities
D.Authorizing stage-level Exception Plans
E.Accepting and checking Work Packages
AnswersA, C, E

Team Managers deliver completed products and provide regular Checkpoint Reports.

Why this answer

The Team Manager accepts/rejects Work Packages, creates Team Plans, executes the work, and delivers completed products to the Project Manager.

3
MCQmedium

During the Initiating a Project (IP) process, how does the Project Manager establish the governance structure for the project?

A.By designing the project management team structure and defining role descriptions in the PID.
B.By outsourcing all governance responsibilities to an external auditing firm.
C.By letting the Team Managers self-organize their own reporting lines to the Project Board.
D.By having Corporate take over all daily decision-making from the Project Manager.
AnswerA

Setting up the project management team structure and drafting role definitions is a core IP activity.

Why this answer

Establishing the governance structure involves defining the roles and responsibilities across the project management team and documenting them in the PID/Role descriptions.

4
MCQeasy

Which PRINCE2 process is used by the Project Board to provide overall governance and control throughout the life of the project?

A.Managing Product Delivery
B.Directing a Project
C.Initiating a Project
D.Controlling a Stage
AnswerB

Directing a Project (DP) runs concurrently with the delivery processes to provide governance.

Why this answer

Directing a Project is the process used by the Project Board to direct the project from start to finish.

5
MCQeasy

Which process provides the Project Board with the mechanism to authorize a project's initiation?

A.Starting up a Project
B.Directing a Project
C.Controlling a Stage
D.Initiating a Project
AnswerB

DP contains the specific board authorization activities, including authorizing initiation.

Why this answer

Directing a Project includes the activity 'Authorizing initiation', where the Project Board reviews the SU outputs and authorizes IP.

6
MCQhard

A project is operating under the Directing a Project (DP) process. The Executive leaves the organization unexpectedly. What action must the Project Board and Corporate level take within the DP framework?

A.The Project Manager automatically assumes the Executive role and approves their own reports.
B.Corporate must appoint a replacement Executive to maintain governance and business justification.
C.The project must be permanently closed immediately without appointing a successor.
D.The Senior Supplier takes over executive responsibilities and project funding.
AnswerB

The Executive role cannot remain vacant; Corporate must appoint a new individual.

Why this answer

Under PRINCE2, the Executive is a mandatory Project Board role. If the Executive leaves, Corporate must appoint a replacement to maintain project governance.

7
Multi-Selectmedium

Which THREE of the following activities are performed during the Managing a Stage Boundary (SB) process?

Select 3 answers
A.Updating the Business Case
B.Planning the next stage
C.Preparing the End Stage Report
D.Executing specialist Work Packages
E.Appointing the initial Project Manager
AnswersA, B, C

The Business Case is updated to reflect current costs and viability before the next stage.

Why this answer

Managing a Stage Boundary includes planning the next stage, updating the Business Case, and preparing an End Stage Report.

8
MCQeasy

Which PRINCE2 process includes the activity 'Capturing and sharing lessons' as a continuous operational habit throughout the project lifecycle?

A.Starting up a Project
B.Closing a Project
C.Controlling a Stage
D.Managing Product Delivery
AnswerC

Controlling a Stage includes capturing lessons learned during day-to-day management.

Why this answer

Capturing and sharing lessons is an ongoing activity that starts in Starting up a Project and continues across Controlling a Stage and other delivery processes.

9
Multi-Selectmedium

Which THREE of the following activities are part of the Controlling a Stage (CS) process?

Select 3 answers
A.Authorizing project closure
B.Preparing the initial Project Brief
C.Authorizing a Work Package
D.Capturing and assessing issues and risks
E.Reviewing work package status
AnswersC, D, E

The Project Manager authorizes Work Packages to Team Managers under CS.

Why this answer

Controlling a Stage includes authorizing work packages, reviewing work package status, and capturing and assessing issues and risks.

10
MCQmedium

During the Closing a Project process, why is it important to archive the project records and documentation?

A.To overwrite the original Business Case with fictional success metrics.
B.To ensure historical project records are securely stored for future audits and organizational learning.
C.To keep the project officially open so the Project Manager continues receiving a salary.
D.To allow the Project Board to continue managing daily work packages indefinitely.
AnswerB

Archiving secures project documentation for governance and future reference.

Why this answer

Archiving project records during Closing a Project ensures historical data is retained for future audits, organizational learning, and reference.

11
MCQhard

A project is operating under the Controlling a Stage (CS) process. A supplier has delivered a Work Package product, but the quality inspection reveals that it does not meet the specified tolerance. What action should the Project Manager take under CS?

A.Escalate immediately to the Project Board requesting project closure.
B.Initiate the Closing a Project process immediately.
C.Raise an issue and instruct the Team Manager to rectify the defect, ensuring it remains within stage tolerances.
D.Accept the defective product anyway and update the Project Product Description to match the substandard output.
AnswerC

The PM manages quality non-conformance via issue handling and instructs remediation within tolerances.

Why this answer

Under Controlling a Stage, when a delivered product fails quality inspection, the Project Manager must log it as a quality issue/defect and instruct the Team Manager (or supplier) to rectify it within stage tolerances.

12
MCQmedium

A Project Manager is managing a stage using the Controlling a Stage process. A Team Manager reports that a Work Package will complete ahead of schedule and under budget. How should the Project Manager handle this positive variance?

A.Automatically extend the project deadline by the saved amount
B.Close the entire project immediately
C.Immediately return the saved money to corporate treasury without informing anyone
D.Capture the variance in a Highlight Report and review stage-level impact
AnswerD

Positive tolerances are reported via Highlight Reports and managed at the stage boundary or within stage controls.

Why this answer

Positive variances (gains in time or cost) within a Work Package belong to the stage and are managed via the stage tolerances. The Project Manager reviews how to utilize this gain within the stage or reports it in the Highlight Report.

13
MCQhard

A project is executing the Managing Product Delivery (MP) process. A Team Manager identifies that a Work Package cannot be completed within the agreed time due to an unforeseen technical bottleneck. What must the Team Manager do?

A.Directly submit an Exception Report to the Project Board.
B.Cancel the entire stage and re-plan the project.
C.Extend the Work Package end date unilaterally without notifying anyone.
D.Raise an issue and alert the Project Manager so that corrective action or escalation can be initiated.
AnswerD

The Team Manager must report roadblocks to the Project Manager via issue escalation.

Why this answer

Under MP, if a Team Manager realizes a Work Package cannot be delivered within its agreed tolerance, they must raise an issue and notify the Project Manager immediately.

14
MCQeasy

Which PRINCE2 process is specifically responsible for creating the Project Management Plan and establishing the baseline against which the project will be managed?

A.Initiating a Project
B.Managing a Stage Boundary
C.Controlling a Stage
D.Starting up a Project
AnswerA

Initiating a Project (IP) is the process where the Project Management Plan and its components are created.

Why this answer

The Initiating a Project process is designed to create the Project Management Plan, establishing all baselines and governance controls.

15
MCQhard

A project is executing the Controlling a Stage process. The Project Manager identifies that multiple minor issues are occurring simultaneously, causing friction among team members. The Project Manager wants to capture these issues formally for ongoing management. Where should they be recorded?

A.Issue Register
B.Daily Log
C.Risk Register
D.Highlight Report
AnswerA

Formal issues affecting the project are logged and tracked in the Issue Register.

Why this answer

Formal issues are recorded in the Issue Register during the Controlling a Stage process.

16
MCQeasy

What is the primary purpose of the Starting up a Project process?

A.To construct all specialist products and deliver them to the operational environment.
B.To ensure that the prerequisites for initiating a project are in place.
C.To close the project and archive all project records.
D.To manage the day-to-day execution of work packages.
AnswerB

SU acts as a pre-project filter to prevent embarking on poorly conceived projects.

Why this answer

Starting up a Project ensures that the prerequisites for initiating a project are in place by answering 'Do we have a viable and worthwhile project to initiate?'.

17
MCQmedium

During the Starting up a Project process, what is the primary purpose of appointing the Project Manager?

A.To enable the Project Manager to plan the initiation stage and prepare the Project Brief.
B.To delegate full financial accountability for the entire project budget to the Project Manager.
C.To allow the Project Manager to authorize project closure independently.
D.To replace the Executive on the Project Board.
AnswerA

The appointed PM executes the remainder of SU and plans IP.

Why this answer

Appointing the Project Manager during SU ensures there is someone designated to plan the initiation stage and manage the pre-project activities.

18
MCQmedium

In the Controlling a Stage (CS) process, how does the Project Manager handle highlight reports?

A.Submit them to the Corporate/Programme level to request additional project funding.
B.Issue them daily to all Team Managers to track individual task completion.
C.Use them as the final evaluation document when closing the project.
D.Create and submit them to the Project Board at agreed intervals to report stage progress.
AnswerD

Highlight reports provide the Project Board with regular updates on progress against stage tolerances.

Why this answer

Highlight reports are produced by the Project Manager at agreed intervals and sent to the Project Board to summarize stage progress.

19
Multi-Selectmedium

Which TWO of the following activities are performed during the Starting up a Project (SU) process?

Select 2 answers
A.Authorizing the Project Management Plan
B.Preparing the Project Brief
C.Executing all Work Packages for specialist delivery
D.Appointing the Executive and Project Manager
E.Conducting the final post-project benefit review
AnswersB, D

The Project Brief is created during SU based on the project mandate.

Why this answer

Starting up a Project includes appointing the management team (Project Manager, etc.) and preparing the Project Brief, as well as planning the initiation stage.

20
MCQhard

A Project Manager is executing the Managing a Stage Boundary process. Halfway through compiling the End Stage Report, a major external market shift invalidates a key assumption in the Business Case. What should the Project Manager do?

A.Ignore the shift, as the End Stage Report only reflects past stage performance
B.Include the impact in the End Stage Report and recommend an Exception Plan or project closure
C.Stop the current stage immediately without consulting the Project Board
D.Immediately rewrite the Business Case and submit it to Corporate
AnswerB

The End Stage Report must highlight the status of the Business Case, and if viability is lost, recommend closing the project or creating an Exception Plan.

Why this answer

The Project Manager must raise an Issue (or reflect it in the End Stage Report and escalate immediately) because an invalid assumption threatening viability requires Project Board intervention via an Exception Report or stage boundary adjustment.

21
Multi-Selectmedium

Which TWO of the following roles are actively involved in the Managing Product Delivery (MP) process?

Select 2 answers
A.Corporate/Programme management
B.Senior Supplier only
C.Team Manager
D.Project Manager
E.Executive
AnswersC, D

The Team Manager executes the MP process.

Why this answer

The Project Manager and the Team Manager are the key roles interacting within Managing Product Delivery.

22
Multi-Selecthard

Which TWO of the following actions are mandatory when executing the Closing a Project (CP) process?

Select 2 answers
A.Drafting a new Project Brief for a follow-on project
B.Handing over products and ensuring operational support arrangements are in place
C.Rewriting the Project Product Description to reflect reduced scope
D.Authorizing the next stage plan for immediate execution
E.Evaluating the project by comparing actual performance against the baseline
AnswersB, E

Product handover and operational support confirmation are required in CP.

Why this answer

Closing a Project requires handing over products and evaluating the project (creating the End Project Report).

23
MCQmedium

During the Initiating a Project process, the Project Manager is refining the Business Case. What key financial metric is typically evaluated to ensure the project represents value for money?

A.Daily checkpoint report frequency
B.Return on Investment (ROI) or Net Present Value (NPV)
C.Team member daily hourly wages
D.Number of open risks in the Risk Register
AnswerB

Financial appraisal techniques like ROI and NPV are used in the Business Case during IP.

Why this answer

During IP, financial metrics such as Return on Investment (ROI), Net Present Value (NPV), or payback period are refined in the Business Case.

24
MCQeasy

When executing the Closing a Project process, who is responsible for confirming handover and acceptance of the project's products?

A.The Project Board Executive
B.Project Assurance
C.The Customer / User
D.Project Manager
AnswerC

The customer or user must formally accept and confirm handover of the project products.

Why this answer

Handover and acceptance of the project products must be confirmed by the customer or user before final project closure.

25
MCQeasy

Which PRINCE2 process provides the interface between the management of the project and the day-to-day creation of the project's specialist products?

A.Starting up a Project
B.Directing a Project
C.Managing Product Delivery
D.Controlling a Stage
AnswerC

Managing Product Delivery (MP) controls the link between the Project Manager and Team Manager for creating specialist products.

Why this answer

Managing Product Delivery is the process that sits between the Project Manager and the Team Manager(s) to execute Work Packages.

26
Multi-Selectmedium

A project is experiencing severe difficulties in the current delivery stage. The Project Manager determines that stage tolerances will be exceeded. Which TWO documents or reports are directly involved in handling this exception situation?

Select 2 answers
A.Checkpoint Report
B.Daily Log
C.Project Brief
D.Exception Report
E.Exception Plan
AnswersD, E

The Project Manager uses an Exception Report to formally notify the Project Board of a tolerance breach.

Why this answer

An Exception Report is raised by the Project Manager to inform the Board, and if accepted, an Exception Plan is created to replace the remainder of the current stage.

27
Multi-Selecthard

Which THREE of the following are specific responsibilities of the Project Board within the Directing a Project (DP) process?

Select 3 answers
A.Maintaining the daily Risk Log and Issue Register
B.Authorizing initiation
C.Drafting individual Work Package Descriptions
D.Authorizing a stage or Exception Plan
E.Authorizing project closure
AnswersB, D, E

The Project Board authorizes the transition from SU to IP.

Why this answer

The Project Board authorizes initiation, authorizes stages/exception plans, and authorizes project closure within DP.

28
MCQhard

A project is currently executing the Controlling a Stage (CS) process. A new risk is identified that threatens the achievement of the stage objectives and exceeds the Project Manager's risk budget. What must the Project Manager do under CS?

A.Rewrite the Business Case to remove the affected benefits.
B.Close the project immediately without consulting anyone.
C.Absorb the risk cost by secretly cutting quality checks on other Work Packages.
D.Escalate the risk to the Project Board via an Issue Report or Exception Report.
AnswerD

Risks exceeding stage tolerances or project budgets must be escalated to the Project Board for guidance or exception handling.

Why this answer

When an issue or risk exceeds the Project Manager's authority or tolerances (including risk budget), the Project Manager must escalate it to the Project Board using an Exception Report or Issue Report.

29
MCQhard

A project is operating under the Controlling a Stage (CS) process. The Project Manager needs to handle a request for change that impacts the Project Product Description. Who must approve this change before the Project Manager can incorporate it?

A.The Project Board
B.The Project Assurance role independently
C.The Project Manager
D.The Team Manager
AnswerA

Changes affecting project-level baselines such as the Project Product Description must be approved by the Project Board.

Why this answer

Changes that impact the Project Product Description (or baselines defined in the PID/Business Case) are outside Project Manager stage tolerances and must be escalated to the Project Board for approval.

30
Multi-Selectmedium

A project is in the Initiating a Project process. Which TWO of the following management approaches must be created or updated during this process?

Select 2 answers
A.Highlight Report template for the Board
B.Risk Management Approach
C.Issue Management Approach
D.End Stage Report for the initiation stage
E.Team Plan for the first work package
AnswersB, C

The Risk Management Approach defines how risks will be identified, assessed, and controlled during the project.

Why this answer

The Risk Management Approach and Issue Management Approach (among other strategies) are created/updated during Initiating a Project.

31
MCQeasy

A Project Manager is drafting the Project Brief during the Starting up a Project process. Which role is primarily responsible for approving the Project Brief before the Project Board is asked to authorize initiation?

A.Executive
B.Project Assurance
C.Project Manager
D.Project Support
AnswerA

The Executive reviews and approves the Project Brief prior to submitting it to the Project Board for the authorizing initiation decision.

Why this answer

The Project Manager compiles the Project Brief during Starting up a Project, but the Executive is accountable for ensuring it is sound and usually approves it before submission to the Project Board.

32
MCQeasy

Which PRINCE2 process runs from the initial pre-project phase until the project is successfully initiated or aborted?

A.Initiating a Project
B.Controlling a Stage
C.Directing a Project
D.Starting up a Project
AnswerD

Starting up a Project is designed as a brief pre-project process.

Why this answer

Starting up a Project is the pre-project process that runs until the Project Board decides whether to authorize initiation.

33
MCQeasy

During the Initiating a Project process, the Project Manager must prepare the Project Plan. What does this plan specifically cover?

A.Post-project operational maintenance schedules
B.The entire project's timescales, costs, and major products across all stages
C.Only the activities of the Starting up a Project process
D.Detailed weekly tasks for the immediate delivery team only
AnswerB

The Project Plan provides a view of the entire project's schedule and budget.

Why this answer

The Project Plan covers the whole project, detailing total costs, timescales, and major products across all stages.

34
Multi-Selecteasy

Which TWO of the following documents are typically produced or updated during the Managing a Stage Boundary (SB) process?

Select 2 answers
A.Project Mandate
B.End Project Report
C.Next Stage Plan
D.End Stage Report
E.Initial Project Brief
AnswersC, D

Produced to detail the work for the upcoming stage.

Why this answer

Managing a Stage Boundary produces the End Stage Report and the Next Stage Plan.

35
MCQmedium

During the Initiating a Project process, the Project Manager is defining the Change Control Approach. What is the primary purpose of this approach?

A.To outline how staff members will be hired and dismissed during the project.
B.To determine how financial invoices are paid to external suppliers.
C.To establish how benefits will be measured post-project.
D.To specify how potential issues and changes to baselined products will be logged, assessed, and controlled.
AnswerD

This is the core definition and purpose of the Change Control Approach.

Why this answer

The Change Control Approach defines how issues and requests for change will be identified, logged, evaluated, and decided upon throughout the project.

36
MCQmedium

During Starting up a Project (SU), the Project Manager is drafting the Project Brief. The Corporate/Programme level wants to know what specific benefits will be achieved, but the exact realization dates and financial metrics are still too uncertain to finalize. How should the Project Manager handle this in the Project Brief?

A.Delay the authorization of the Starting up a Project process until Corporate provides exact financial projections.
B.Leave out the Business Case entirely until the Initiating a Project process is authorized.
C.Include an outline Business Case capturing the expected benefits and general timing, acknowledging that precise metrics will be refined during Initiation.
D.Include a fully detailed Business Case with guaranteed ROI figures to satisfy the Executive.
AnswerC

The outline Business Case is established in SU and forms part of the Project Brief.

Why this answer

In Starting up a Project, the Project Brief includes the outline Business Case, which outlines the expected benefits and alignment, even if exact financial metrics are finalized later during Initiation.

37
MCQmedium

In the Managing Product Delivery (MP) process, what is the purpose of the 'Accepting a work package' activity?

A.To allow the Team Manager to bypass the Project Manager and report directly to the Executive.
B.To authorize the creation of a new stage in the project schedule.
C.To formally close the project and hand over products to operations.
D.To ensure the Team Manager understands and commits to delivering the Work Package within agreed constraints.
AnswerD

Acceptance commits the team to the Work Package terms and quality criteria.

Why this answer

Before executing a Work Package, the Team Manager must formally accept it by ensuring that understanding is aligned, prerequisites are met, and the team can commit to delivering within the constraints.

38
MCQmedium

A Project Manager is executing the Starting up a Project process. They need to appoint the management team for the initiation stage. Who formally appoints the Project Manager for this process?

A.Corporate or Program Management
B.The Executive
C.Project Assurance
D.Lead Team Manager
AnswerA

Corporate or program management initiates the project environment and appoints the Executive and Project Manager.

Why this answer

Corporate or program management appoints the Executive and the Project Manager to run the Starting up a Project process.

39
MCQeasy

What is the primary output of the Initiating a Project (IP) process?

A.End Project Report
B.Project Initiation Documentation (PID)
C.Work Package Description
D.Project Brief
AnswerB

The PID is the foundational document compiled during IP.

Why this answer

The primary output of Initiating a Project is the Project Initiation Documentation (PID).

40
MCQeasy

Which process covers the activities undertaken by the Project Board to appoint the Project Manager and authorize the project mandate transition?

A.Closing a Project
B.Managing Product Delivery
C.Controlling a Stage
D.Starting up a Project
AnswerD

Starting up a Project sets up the pre-project governance and appoints roles.

Why this answer

Starting up a Project is where the pre-project setup, including management appointment and Project Brief drafting, occurs under board oversight.

41
MCQmedium

During the Initiating a Project (IP) process, the Project Manager needs to establish the project's schedule and resource requirements. Where should these be compiled?

A.In the Highlight Report
B.In the Project Management Plan
C.In the Project Brief
D.In the End Project Report
AnswerB

The Project Management Plan contains the overall schedule, resource allocations, and stage plans.

Why this answer

The schedule and resource requirements form part of the Project Management Plan, which is compiled during IP.

42
Multi-Selectmedium

During the Starting up a Project process, the Project Manager must design and appoint the project management team. Which TWO roles must be defined and filled during this process?

Select 2 answers
A.The Executive
B.Independent external auditors
C.Corporate Change Champions
D.The Project Manager
E.Specialist Team Managers for all delivery stages
AnswersA, D

The Executive must be appointed during Starting up a Project so there is business ownership.

Why this answer

Starting up a Project requires appointing the Executive and the Project Manager.

43
MCQmedium

A project is in the Starting up a Project process (SU). The Executive wants to know how long SU should take and what its primary output is. Which statement is correct?

A.SU is executed by the Project Board to write the detailed Project Plan.
B.SU lasts for the duration of the first delivery stage and delivers the final product.
C.SU is a pre-project process whose main output is the Project Brief and the Initiation Stage Plan.
D.SU replaces the Initiating a Project process for small projects.
AnswerC

SU establishes whether it is worth initiating a project, resulting in the Project Brief and Initiation Stage Plan.

Why this answer

Starting up a Project is a short, pre-project process designed to ensure it is worthwhile to initiate the project. Its key output is the Project Brief and Initiation Stage Plan.

44
MCQmedium

In the Controlling a Stage (CS) process, how does the Project Manager handle ad-hoc requests for change originating from stakeholders?

A.Capture the request in the Issue Register, assess its impact, and process it according to the Change Control Approach.
B.Reject all change requests automatically to prevent scope creep.
C.Implement the change immediately to satisfy the stakeholder without logging it.
D.Forward the change request directly to the Team Manager with instructions to build it without approval.
AnswerA

All change requests follow formal issue and change control procedures.

Why this answer

Under CS, ad-hoc requests for change must be captured in the Issue Register as a request for change and assessed for impact before being decided upon.

45
MCQeasy

Which PRINCE2 process ensures that project closure is orderly and controlled, preventing lingering unfinished work?

A.Starting up a Project
B.Closing a Project
C.Managing a Stage Boundary
D.Controlling a Stage
AnswerB

Closing a Project (CP) provides a controlled end to project execution.

Why this answer

Closing a Project ensures an orderly closure by verifying handover, evaluating performance, and recommending follow-on actions.

46
Multi-Selecthard

A Project Manager is executing the Closing a Project process. Which THREE of the following actions are mandatory requirements of this process?

Select 3 answers
A.Recommending follow-on action recommendations for uncompleted issues or maintenance
B.Rewriting the Business Case to reflect actual total costs and benefits realized
C.Handing over products and confirming operational acceptance
D.Evaluating the project by comparing it against the baselined PID
E.Appointing new members to the Project Board for post-project governance
AnswersA, C, D

Follow-on action recommendations must be prepared for things like uncompleted work or future maintenance.

Why this answer

Closing a Project requires preparing a planned closure, handing over products, evaluating the project, and recommending follow-on actions.

47
MCQhard

A project is in the Closing a Project (CP) process. The Project Board is evaluating whether to authorize closure. Which of the following conditions must be met for the Project Board to authorize project closure?

A.The Project Manager has received a performance bonus from the Senior Supplier.
B.All risks in the risk log have been completely eliminated with zero residual risk.
C.Project objectives have been achieved, products handed over, and follow-on action recommendations documented.
D.All benefits have been fully realized and measured in the operational environment.
AnswerC

These are the mandatory completion criteria verified during Closing a Project.

Why this answer

To authorize project closure, the Project Board must ensure that project objectives as defined in the PID/Project Product Description have been met, handover is complete, and follow-on actions are documented.

48
MCQhard

A project is undergoing the Closing a Project process. The Project Board requests confirmation that all project benefits have been fully realized before giving final approval to close. According to PRINCE2, why is this request problematic at this exact moment?

A.Benefits are managed exclusively by Team Managers during Managing Product Delivery.
B.The Project Board has no authority to review benefits.
C.Benefits realization reviews occur post-project and cannot be completed during the Closing a Project process.
D.The Project Manager is prohibited from measuring benefits.
AnswerC

Benefits realization often happens months or years after project closure; the project closure process only sets up the Benefit Review Plan for future assessment.

Why this answer

Many project benefits materialize long after the project products are handed over and the project is closed; therefore, benefit realization cannot be fully proven at project closure.

49
Multi-Selecteasy

Which THREE PRINCE2 processes are managed primarily by the Project Manager?

Select 3 answers
A.Directing a Project
B.Managing Product Delivery
C.Controlling a Stage
D.Initiating a Project
E.Managing a Stage Boundary
AnswersC, D, E

CS is managed day-to-day by the Project Manager.

Why this answer

Initiating a Project, Controlling a Stage, and Managing a Stage Boundary are managed by the Project Manager.

50
MCQeasy

Which PRINCE2 process focuses on planning the next stage, updating the Business Case, and reviewing the performance of the current stage?

A.Controlling a Stage
B.Directing a Project
C.Managing a Stage Boundary
D.Starting up a Project
AnswerC

Managing a Stage Boundary (SB) is executed near the end of each stage to plan the next one and assess the current one.

Why this answer

Managing a Stage Boundary is specifically designed to enable the Project Board to be provided with sufficient information to review the success of the current stage, approve the next stage plan, and confirm continued business justification.

51
Multi-Selecthard

Which TWO of the following statements correctly describe the Managing Product Delivery (MP) process?

Select 2 answers
A.It is executed by the Project Board to govern stage boundaries.
B.It provides the interface between the Project Manager and the Team Manager.
C.It is responsible for authorizing the overall Project Initiation Documentation.
D.It replaces the Controlling a Stage process entirely.
E.It ensures that work on products is focused, controlled, and delivered.
AnswersB, E

MP governs how Work Packages are accepted, executed, and returned.

Why this answer

Managing Product Delivery ensures that work is received, executed, and delivered between the Project Manager and Team Manager.

52
Multi-Selecthard

A PRINCE2 project is reaching its conclusion. Which THREE criteria must be satisfied to consider the Closing a Project process properly structured and executed?

Select 3 answers
A.Provision is made for follow-on actions and post-project benefits reviews
B.The project performance is evaluated against the baseline PID
C.All future benefits have already been fully realized and verified
D.The Project Board remains active indefinitely to maintain operational support
E.Handover of products is confirmed and operational acceptance is secured
AnswersA, B, E

Follow-on actions and benefit review plans must be established.

Why this answer

Proper project closure requires confirming handover, evaluating project performance against the PID, and ensuring no unmanaged commitments remain.

53
MCQhard

A project is in the Managing a Stage Boundary (SB) process. The Project Manager is preparing the End Stage Report. Which of the following elements must be included in this report to give the Project Board a complete view of stage performance?

A.A review of how the stage performed against its planned cost, time, scope, and quality tolerances.
B.A detailed personnel evaluation and salary review for all project team members.
C.A request to dissolve the corporate organization.
D.The final benefit realization audit conducted 5 years post-project.
AnswerA

The End Stage Report focuses on comparing actuals against the stage plan tolerances.

Why this answer

The End Stage Report compares actual performance (cost, time, scope, quality) against the Stage Plan and summarizes project progress to date.

54
Multi-Selectmedium

Which TWO of the following statements describe the relationship between Starting up a Project (SU) and Initiating a Project (IP)?

Select 2 answers
A.IP is managed by Team Managers while SU is managed by Corporate.
B.IP takes the Project Brief from SU and builds the comprehensive Project Management Plan.
C.SU is a pre-project process designed to determine whether a project is worth initiating.
D.IP must be completed before SU can even begin.
E.SU produces the final baselined Project Management Plan.
AnswersB, C

IP uses the Project Brief as its primary input to create the PID/PMP.

Why this answer

SU is a pre-project process designed to prevent wasted effort, while IP is the formal first stage of the project where detailed planning occurs.

55
Multi-Selecthard

Which THREE of the following inputs are required when executing the Initiating a Project (IP) process?

Select 3 answers
A.The Project Mandate
B.Direction from the Project Board (via DP)
C.Completed Work Package delivery sign-offs
D.The Project Brief
E.The End Project Report from the previous project
AnswersA, B, D

The original mandate provides initial context and direction.

Why this answer

Key inputs to IP include the Project Brief (from SU), the Project Mandate, and guidance from Directing a Project.

56
MCQhard

A project is currently in the Directing a Project (DP) process. An issue has arisen that exceeds the Project Manager's delegated stage tolerance, and the Project Manager has submitted an Exception Report. The Project Board wants to review the options and authorize an alternative way forward without prematurely closing the project. Which DP activity should the Project Board perform?

A.Authorizing a stage or Exception Plan.
B.Initiating a project.
C.Authorizing project closure.
D.Capturing and sharing lessons.
AnswerA

The Project Board uses this activity in DP to review and approve the Exception Plan resulting from an escalated issue.

Why this answer

When an Exception Report is submitted, the Project Board uses the 'Giving ad hoc direction' activity to respond to the exception, or specifically 'Authorizing a project or stage plan' if they are approving an Exception Plan.

57
MCQmedium

During the Initiating a Project (IP) process, the Project Manager is setting up controls. Which activity involves defining how issues and risks will be logged, assessed, and managed throughout the project?

A.Assembling the Project Management Plan
B.Refining the Business Case
C.Preparing the Project Initiation Documentation
D.Setting up the project controls
AnswerD

This activity establishes the management approaches and control mechanisms documented in the PID.

Why this answer

In Initiating a Project, setting up the project controls includes establishing the Change Control Approach, Risk Management Approach, and other strategies.

58
Multi-Selectmedium

Which THREE of the following are objectives of the Closing a Project (CP) process?

Select 3 answers
A.Verify user acceptance of project products
B.Create the baseline Project Management Plan
C.Evaluate project performance against the PID baselines
D.Authorize the execution of the next delivery stage
E.Ensure provision is made for post-project benefit reviews
AnswersA, C, E

Ensures products meet expectations and handover is accepted.

Why this answer

Closing a Project aims to verify product handover, evaluate project performance, and ensure follow-on actions are recorded.

59
Multi-Selecthard

A project is in the Directing a Project process. Which THREE of the following decisions represent formal responsibilities of the Project Board within this process?

Select 3 answers
A.Authorizing project initiation
B.Authorizing project closure
C.Drafting the detailed Team Plans for specialist delivery
D.Writing the Project Initiation Documentation
E.Authorizing a Stage Plan or Exception Plan
AnswersA, B, E

The Project Board authorizes initiation at the end of Starting up a Project.

Why this answer

The Project Board authorizes initiation, authorizes stage plans (or exception plans), and authorizes project closure.

60
MCQeasy

Which PRINCE2 process is triggered immediately after the Project Board authorizes the initiation of a project?

A.Closing a Project
B.Managing Product Delivery
C.Controlling a Stage
D.Initiating a Project
AnswerD

Once SU concludes and the Board authorizes initiation, the IP process begins.

Why this answer

Initiating a Project is the process triggered right after the Project Board authorizes the request to initiate coming from Starting up a Project.

61
MCQeasy

In the Controlling a Stage process, what is the primary purpose of regular Checkpoint Reports submitted by Team Managers to the Project Manager?

A.To evaluate the overall Business Case viability for the whole project
B.To report progress on Work Packages against agreed Work Package tolerances
C.To formally close completed specialist products
D.To request authorization for the next stage from the Project Board
AnswerB

Checkpoint Reports are used by Team Managers to report the status of Work Packages to the Project Manager.

Why this answer

Checkpoint Reports provide the Project Manager with progress updates on individual Work Packages against agreed tolerances.

62
MCQeasy

Which PRINCE2 process is responsible for creating the detailed plan for the stage immediately following initiation?

A.Initiating a Project
B.Directing a Project
C.Starting up a Project
D.Managing a Stage Boundary
AnswerA

IP plans the first delivery stage alongside creating the PID.

Why this answer

Initiating a Project includes creating the Project Initiation Documentation and the Stage Plan for the first delivery stage.

63
MCQmedium

During the Initiating a Project process, the Project Manager needs to define how issues and risks will be managed, tracked, and controlled. Which document or strategy should contain these procedures?

A.Daily Log
B.Project Brief
C.Stage Plan for the next delivery stage
D.Risk Management Approach and Issue Management Approach
AnswerD

Approaches defining how risks and issues will be handled are created or refined during Initiating a Project.

Why this answer

The Control approach (part of the overall management approaches or strategies in PRINCE2) defines how issues, risks, and changes are managed.

64
MCQmedium

In the Directing a Project (DP) process, when is the Project Board required to authorize the Project Initiation Documentation (PID)?

A.During the Starting up a Project process before appointing the Project Manager.
B.During the Closing a Project process.
C.At the end of the Initiating a Project process, as part of authorizing the project.
D.At the start of every single delivery stage.
AnswerC

The Project Board reviews and authorizes the PID and the project as the final step of the Initiating a Project process.

Why this answer

The Project Board authorizes the PID during the 'Authorizing initiation' activity or more accurately, authorizes the project itself based on the PID during 'Authorizing a project'.

65
MCQmedium

During the Controlling a Stage (CS) process, the Project Manager identifies that a work package is likely to exceed its time tolerance due to supplier delays. What is the immediate first action the Project Manager should take under CS?

A.Immediately rewrite the Project Initiation Documentation and submit it to Corporate.
B.Cancel the work package and award it to a different supplier without consulting the Project Board.
C.Wait until the end of the stage before notifying the Project Board of the delay.
D.Raise an issue, assess its impact, and prepare an Exception Report if tolerances are forecast to be exceeded.
AnswerD

This follows the 'Reviewing work package status' and 'Capturing and assessing issues and risks' activities within CS.

Why this answer

Under Controlling a Stage, when a forecast indicates a tolerance will be breached, the Project Manager must raise an Issue and assess its impact before escalating to the Project Board.

66
MCQmedium

In the Controlling a Stage (CS) process, how does the Project Manager use checkpoint reports?

A.Publish checkpoint reports to external stakeholders as public marketing releases.
B.Send checkpoint reports to Corporate to authorize stage boundaries.
C.Review checkpoint reports submitted by Team Managers to monitor Work Package progress.
D.Submit checkpoint reports to the Project Board to report stage exception statuses.
AnswerC

Checkpoint reports are the mechanism by which Team Managers report to the Project Manager.

Why this answer

Checkpoint reports are received by the Project Manager from Team Managers to monitor progress on Work Packages.

67
MCQhard

In the Managing Product Delivery (MP) process, a Team Manager is executing a Work Package. The Team Manager discovers that a specialist product cannot be built to the quality criteria specified in the Work Package Description due to technological limitations. What should the Team Manager do first?

A.Raise an issue and inform the Project Manager so that the impact on stage tolerances can be assessed.
B.Escalate directly to the Project Board, bypassing the Project Manager.
C.Pause the Work Package indefinitely until the supplier figures out a workaround.
D.Change the quality criteria directly to match what the team can achieve and record it in the Team Plan.
AnswerA

The Team Manager works under the direction of the Project Manager and must escalate issues via 'Reviewing and reporting work package status'.

Why this answer

In MP, if a problem occurs that affects a Work Package, the Team Manager must raise an issue (or notify the Project Manager) rather than unilaterally changing quality criteria.

68
MCQeasy

In the Directing a Project process, how does the Project Board primarily exercise its day-to-day governance over the project's progress?

A.By directly managing Team Managers and assigning Work Packages
B.By attending daily stand-up meetings with the delivery team
C.By reviewing Highlight Reports provided by the Project Manager
D.By rewriting the Project Plan whenever a minor delay occurs
AnswerC

The Project Board uses Highlight Reports to monitor ongoing stage progress and exceptions.

Why this answer

The Project Board reviews Highlight Reports submitted periodically by the Project Manager to monitor stage progress against tolerances.

69
Multi-Selecthard

Which THREE of the following actions are valid responses by the Project Board when an Exception Report is escalated during Controlling a Stage?

Select 3 answers
A.Instruct project closure if the project is no longer viable
B.Request an Exception Plan to be prepared and submitted for approval
C.Direct the Project Manager to alter stage tolerances without a plan
D.Take over day-to-day management of the work packages directly from the Team Managers
E.Authorize an alternative stage plan or Exception Plan
AnswersA, B, E

If exceptions destroy business justification, the board can close the project.

Why this answer

When an Exception Report is submitted, the Project Board can request a revised Exception Plan, instruct project closure, or authorize another stage plan.

70
MCQhard

During the Managing a Stage Boundary (SB) process, the Project Manager prepares an Exception Plan. Under what circumstances is this plan created and submitted?

A.When a Team Manager fails to complete a single Work Package on time.
B.When the Project Board wants to prematurely close the project due to corporate budget cuts.
C.Automatically at the end of every successful stage, regardless of performance.
D.When forecasts show that stage tolerances are about to be breached, replacing the current stage or remaining project plan.
AnswerD

An Exception Plan is drawn up to replace the uncompleted part of a stage when tolerances are forecast to be exceeded.

Why this answer

An Exception Plan is created when current stage forecasts indicate that stage tolerances will be exceeded, and it is submitted during SB or CS (depending on when the exception occurs) for Project Board approval.

71
MCQmedium

During the Closing a Project (CP) process, the Project Manager is handing over products. Which activity ensures that ongoing maintenance, operations, and support arrangements for the project products are formally accepted by the host organization?

A.Evaluating the project
B.Updating the Project Management Plan
C.Handing over products
D.Preparing the End Stage Report
AnswerC

This activity ensures operational handover and acceptance of maintenance responsibilities.

Why this answer

In Closing a Project, 'Handing over products' involves confirming that operational and maintenance arrangements are in place and accepted by the user/operational organization.

72
MCQhard

A project is operating under the Directing a Project (DP) process. The Project Board is reviewing an End Stage Report and a Next Stage Plan. What key decision must the Project Board make during this activity?

A.Whether to take over day-to-day management from the Project Manager for the upcoming stage.
B.Whether to authorize the next stage plan, confirming continued business justification.
C.Whether to rewrite the entire Project Product Description for the next stage.
D.Whether to dismiss the Senior Supplier for stage delays without reviewing the exception report.
AnswerB

The Project Board authorizes stage plans in DP ('Authorizing a stage or Exception Plan').

Why this answer

When reviewing an End Stage Report and Next Stage Plan in Managing a Stage Boundary / Directing a Project, the Project Board must decide whether to authorize the next stage, amend it, or reject it based on continued viability.

73
MCQmedium

During the Closing a Project (CP) process, who is responsible for preparing the End Project Report?

A.Project Assurance
B.The Corporate/Programme management
C.The Project Manager
D.The Executive
AnswerC

The Project Manager drafts the End Project Report to evaluate project performance.

Why this answer

The Project Manager prepares the End Project Report during Closing a Project for submission to the Project Board.

74
MCQhard

A project is in the Starting up a Project (SU) process. The Project Manager has appointed the management team, prepared the project brief, and is now planning the initiation stage. What is the final activity the Project Manager must perform in SU before submitting the request to initiate the project to the Project Board?

A.Approving the detailed Stage Plans for the entire project life cycle.
B.Planning the initiation and requesting authorization to initiate the project.
C.Authorizing the Project Management Plan.
D.Conducting a formal End Project Evaluation.
AnswerB

The final activity of SU is planning the initiation stage and submitting the request to initiate to the Project Board.

Why this answer

The final activity in Starting up a Project is 'Planning the initiation', but the last thing done before handing over is 'Handing over the project' (seeking authorization to initiate). Specifically, the process concludes by requesting authorization to initiate the project.

75
MCQmedium

In the Closing a Project (CP) process, what should be done with the project's risks and issues logs that remain unresolved at the time of closure?

A.Escalate them to the Project Board so the board members can resolve them personally before disbanding.
B.Review them and pass them on to corporate or operational management for ongoing post-project tracking.
C.Automatically convert them into new projects under the same Project Manager.
D.Delete them permanently because the project is closing and they are no longer relevant.
AnswerB

Unresolved issues and risks are handed over as part of follow-on action recommendations.

Why this answer

During Closing a Project, any unresolved issues and risks must be reviewed and passed on to the operational/corporate management or customer so they can be managed post-project.

Page 1 of 2 · 89 questions totalNext →