During a project audit, it is discovered that team members are unsure who has the authority to approve design changes because the Project Management Team structure was never formally documented. Which PRINCE2 principle has been violated?
Failing to document organizational structures and authority levels is a direct violation of defined roles and responsibilities.
Why this answer
Defined roles and responsibilities requires an organization to have a clear, documented organizational structure involving business, user, and supplier interests, ensuring everyone knows their authority levels.