During a Sprint Review, the Product Owner presents the current state of the Product Backlog and projected delivery dates based on the team's recent velocity. A stakeholder challenges the accuracy of these projections, and the Developers begin defending their estimates. How should the Scrum Master facilitate the remainder of the event?