A Scrum Master joins a team that has been using Scrum for six months. During the Daily Scrum, the Developers give a detailed status report to the Scrum Master, who then updates the Sprint Burndown Chart and assigns follow-up tasks. The team consistently meets its Sprint Goal, but the Scrum Master is concerned about long-term effectiveness. What should the Scrum Master do first?