During the second iteration of a Program Increment, the Product Owner for Team Delta notices that a dependency on Team Echo is at risk of slipping, which would delay a critical feature. The teams are in different time zones, and the Product Owner wants to address this proactively without waiting for the next Scrum of Scrums. What is the most effective first step?