PK0-005 Project Management Concepts • Set 7
PK0-005 Project Management Concepts Practice Test 7 — 15 questions with explanations. Free, no signup.
The project manager receives a defect report for CI-103. The team identifies that a new requirement necessitates updating CI-103. According to the configuration management process, what should the project manager do FIRST?
Refer to the exhibit. Exhibit: Configuration Item Status Item ID | Version | Status | Last Modified CI-101 | 1.2 | Approved | 2023-10-15 CI-102 | 2.0 | Under Review| 2023-10-20 CI-103 | 1.0 | Approved | 2023-09-01