PK0-005 Project Management Concepts • Set 4
PK0-005 Project Management Concepts Practice Test 4 — 15 questions with explanations. Free, no signup.
You are the project manager for a large infrastructure project that involves upgrading the network switches across five regional offices. The project has a budget of $500,000 and a deadline of six months. During the third month, you receive a report that the vendor has encountered a manufacturing defect in the switches, causing a two-month delay. Additionally, the cost to replace the defective switches will be $100,000 over budget. The project sponsor is concerned about the impact on the business and wants to know the best way to move forward. There is a possibility that the vendor can expedite shipping for an additional $50,000, but it will only save one month. Alternatively, you can switch to a different vendor, but that would require renegotiating contracts and retesting, adding three months to the schedule. Another option is to descope one of the regional offices to reduce costs and time. However, that office is critical for an upcoming product launch. What is the BEST course of action for the project manager?