PK0-005 Project Management Concepts • Set 2
PK0-005 Project Management Concepts Practice Test 2 — 15 questions with explanations. Free, no signup.
Refer to the exhibit. What is the total float for Task D?
Refer to the exhibit. ``` [Project Schedule - Critical Path] Task A (5d) -> Task C (3d) -> Task E (4d) -> Task G (2d) Task B (6d) -> Task D (4d) -> Task F (5d) -> Task H (3d) Dependencies: Task C depends on A and B; Task D depends on B; Task E depends on C; Task F depends on D; Task G depends on E; Task H depends on F. All durations in days. No other dependencies. ```