You are the portfolio manager for a global logistics firm. During the quarterly portfolio performance review, you observe that the aggregate portfolio benefits realization is 15% below the planned target, while individual component dashboards show all projects as green on schedule and cost. What should you do FIRST to address this discrepancy?