A company uses Dynamics 365 Supply Chain Management. They are running Master Planning and need to ensure that the planning process considers both supply and demand within the planning horizon. They have set up a master plan with a coverage code of Requirement. During the planning run, they notice that some planned orders are not being generated for items with a negative inventory balance. Which two configuration settings should they verify to ensure that Master Planning includes all relevant demand? (Choose two.)