MB-330 Implement Master Planning • 30 Questions
30 MB-330 Implement Master Planning practice questions with answers and explanations. Free, no signup.
A company uses coverage groups to manage replenishment. You need to ensure that the Master Planning process ignores demand that occurs before the current date to prevent legacy orders from impacting supply suggestions. Which parameter should you configure?