DP-300 Plan and implement data platform resources • Set 8
DP-300 Plan and implement data platform resources Practice Test 8 — 15 questions with explanations. Free, no signup.
You are tasked with designing a disaster recovery plan for an Azure SQL Database. The database is mission-critical and must have a Recovery Point Objective (RPO) of 5 seconds and a Recovery Time Objective (RTO) of 30 minutes in case of a regional failure. Which configuration should you implement?
Choose an answer to begin — your selection is scored in the full session.
15 questions · instant feedback and full explanations after every question.