PAS-C01 Migration • Set 23
PAS-C01 Migration Practice Test 23 — 15 questions with explanations. Free, no signup.
A company is migrating a large SAP Business Warehouse (BW) system to AWS. The system uses SAP HANA as the database. The migration plan involves using SAP HANA System Replication (HSR) for near-zero downtime. During the initial synchronization, the network bandwidth is limited to 1 Gbps. The source database is 5 TB. How long will the initial synchronization approximately take, assuming no other bottlenecks?
Choose an answer to begin — your selection is scored in the full session.