Which TWO fields on a Change Request form help determine whether a schedule conflict exists? (Choose two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Planned end date

Planned start date and Planned end date are compared against other changes and blackouts.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Planned end date

    Why this is correct

    Planned end date is evaluated by the conflict engine.

  • Assignment group

    Why it's wrong here

    Assignment group indicates who owns the task, not when it runs.

  • Category

    Why it's wrong here

    Category classifies the change type.

  • Planned start date

    Why this is correct

    Planned start date is evaluated by the conflict engine.

  • Short description

    Why it's wrong here

    Short description summarizes the change text.

About these practice questions

This CIS-ITSM question is part of Courseiva's 500-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official ServiceNow exam blueprint

This CIS-ITSM practice question is part of Courseiva's free ServiceNow certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CIS-ITSM exam.