Introducing Scrum in SAFe →mediumMultiple Select

SSM Introducing Scrum in SAFe Practice Question

A Scrum Master is helping a team new to SAFe understand which Scrum events occur within each Iteration and how they connect to ART cadence. Which TWO statements accurately describe this relationship? (Choose two.)

⚠ Common exam trap

The trap here is collapsing ART-level events into team-level events, assuming that attending a train event satisfies the corresponding Scrum event.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Retrospective occurs at the end of each Iteration, and the ART may also hold an Inspect and Adapt event at the end of a Program Increment to address systemic issues.

Scrum events run at the team level inside each Iteration, while PI Planning and the Inspect and Adapt event operate on the ART cadence across a Program Increment. The Iteration Review and System Demo are distinct feedback loops, and the team Retrospective is complemented rather than replaced by the ART-level Inspect and Adapt. Recognizing both cadences helps a new team understand how local Scrum practices connect to train-wide alignment.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    The Retrospective occurs at the end of each Iteration, and the ART may also hold an Inspect and Adapt event at the end of a Program Increment to address systemic issues.

    Why this is correct

    The team Retrospective closes each Iteration by inspecting how the team worked and identifying improvements. In SAFe, the ART additionally holds an Inspect and Adapt event after the System Demo at the end of a Program Increment to solve broader, systemic problems. These operate at different levels and do not replace each other, giving teams both local and train-wide improvement loops.

  • ✓

    Iteration Planning, the Daily Scrum, the Iteration Review, and the Retrospective all occur within the Iteration, while PI Planning occurs on the ART cadence across a Program Increment.

    Why this is correct

    Scrum events operate at the team level inside each Iteration, whereas PI Planning is an ART-level event held at the start of a Program Increment. Understanding that both cadences coexist prevents teams from treating PI Planning as a replacement for Iteration Planning. The Iteration remains the container for the team's Scrum events, and the Program Increment provides the broader alignment context around several Iterations.

  • ✗

    An Iteration is the same length as a Program Increment, so the team holds one Iteration Review per PI and no Retrospective until the PI ends.

    Why it's wrong here

    A Program Increment typically spans several Iterations, so treating them as equal length contradicts SAFe's cadence structure. Holding only one Iteration Review per PI would eliminate the repeated inspect-and-adapt cycles that Scrum depends on and delay feedback for weeks. The Retrospective also occurs each Iteration, not once per PI, though the ART may hold additional Inspect and Adapt activities at PI boundaries.

  • ✗

    The Daily Scrum should be replaced by the ART's Scrum of Scrums, because coordinating dependencies is more valuable than the team's daily inspection.

    Why it's wrong here

    The Daily Scrum is the Developers' event for inspecting progress toward the Sprint Goal and adapting their plan; the Scrum of Scrums is a separate coordination forum for the ART. Replacing one with the other removes the team's internal adaptation and leaves cross-team coordination without a team-level foundation. Both exist for different purposes and cadences, and neither substitutes for the other.

  • ✗

    The Iteration Review and the System Demo are the same event, so a team that attends the System Demo does not need to hold its own Iteration Review.

    Why it's wrong here

    The Iteration Review is a team-level Scrum event where the team and stakeholders inspect the team's Increment, while the System Demo inspects the integrated solution across the ART. They serve different audiences and feedback loops. Skipping the Iteration Review would remove the team's own inspect-and-adapt opportunity and weaken Product Owner validation, even if the team participates in the System Demo.

About these practice questions

Courseiva writes every SSM question from scratch — 385 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.