SAFe-Agilist Establishing Team and Technical Agility Practice Question

An Agile Team is consistently unable to complete its Iteration goals because unplanned work, such as production support and defect fixes, consumes a significant portion of its capacity. The team's Scrum Master wants to address this issue while maintaining technical agility. Which action best aligns with SAFe principles to improve the team's ability to meet its Iteration goals?

⚠ Common exam trap

The trap here is thinking that extending the Iteration or working overtime can solve the capacity problem, when the real solution is to make unplanned work visible and reserve capacity for it.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Reserve a portion of each Iteration's capacity for unplanned work and make it visible in the team's backlog.

Reserving capacity for unplanned work and making it visible in the backlog is the most effective SAFe-aligned approach. It allows the team to plan realistically, maintain a sustainable pace, and provide transparency to stakeholders about the impact of unplanned work. Other options either fail to address the root cause, disrupt the train's cadence, or rely on unsustainable practices like overtime or deferral.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Have the team work overtime to complete both planned and unplanned work.

    Why it's wrong here

    Working overtime is unsustainable and leads to burnout, reduced quality, and increased turnover. SAFe emphasizes sustainable pace as a core principle. Overtime may provide a short-term boost but will degrade the team's long-term productivity and technical agility. It also masks the underlying capacity problem rather than solving it. This option is not a viable or healthy solution for managing unplanned work.

  • ✗

    Extend the Iteration length to three weeks to provide more time to absorb unplanned work.

    Why it's wrong here

    Extending the Iteration length does not reduce the amount of unplanned work; it merely stretches the same problem over a longer period. SAFe promotes a consistent cadence across the Agile Release Train, and changing one team's Iteration length would disrupt synchronization and the System Demo. The root cause of unplanned work remains unaddressed, and the team may still fail to meet its goals. This option does not improve technical agility or predictability.

  • ✓

    Reserve a portion of each Iteration's capacity for unplanned work and make it visible in the team's backlog.

    Why this is correct

    Reserving capacity for unplanned work and making it visible is a SAFe-recommended practice to handle production support without derailing Iteration goals. It acknowledges reality and allows the team to plan more accurately. By making unplanned work visible in the backlog, the team and its stakeholders can see the impact and make informed trade-offs. This practice supports predictability and technical agility by preventing unplanned work from silently eroding capacity.

  • ✗

    Ask the Product Owner to prioritize only planned work and defer all unplanned work to the next Iteration.

    Why it's wrong here

    Deferring all unplanned work is unrealistic and can harm the product and customers. Production support and defect fixes often cannot wait. SAFe encourages teams to make unplanned work visible and manage it, not ignore it. Simply deferring it will lead to a growing backlog of urgent issues and may damage trust with stakeholders. This approach does not address the capacity issue and can increase technical debt over time.

About these practice questions

Courseiva writes every SAFe-Agilist question from scratch — 315 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This SAFe-Agilist practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SAFe-Agilist exam.