A team is moving from a traditional waterfall environment to SAFe. The manager wants to continue using 'Project Milestones' to track progress. Why does SAFe prefer 'Objective Evaluation' instead?

⚠ Common exam trap

Many candidates assume milestone tracking is acceptable if management requests it, falling back on traditional waterfall habits instead of prioritizing empirical working software.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Objective evaluation allows for a more accurate assessment of the solution.

SAFe prioritizes objective evaluation because traditional milestones often provide false confidence. A project might be '80% done' based on a schedule, but without working, tested software, the reality is unknown. Objective evaluation through frequent integration and demonstration ensures that progress is based on empirical reality. This matters because it allows for early detection of integration issues and shifts the conversation from subjective status reports to tangible product reality, minimizing project risk.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Milestones are inherently expensive to track and maintain.

    Why it's wrong here

    The cost of tracking is not the primary issue; the lack of veracity is. Milestones are problematic because they mask the difference between 'completed documentation' and 'working software.' Even if tracking is cheap, if it provides misleading data, it creates a dangerous sense of security that ruins development efforts.

  • ✓

    Objective evaluation allows for a more accurate assessment of the solution.

    Why this is correct

    Objective evaluation relies on working systems, not documentation or status reports. By verifying the solution through iterative development and demonstration, the team gets real feedback on whether the system actually works. This prevents the 'watermelon project' syndrome where things look green on the outside but are red inside.

  • ✗

    Milestones are only used in large-scale government projects.

    Why it's wrong here

    This is factually incorrect. Milestones are widely used across all industries, including commercial software development. The rejection of milestones in SAFe is not based on who uses them, but on the fact that they are not a reliable way to gauge progress in an iterative and complex development environment.

  • ✗

    Objective evaluation is the only way to satisfy regulatory compliance.

    Why it's wrong here

    Regulatory compliance can often be handled through traditional documentation. However, SAFe principles advocate for evaluation based on actual system performance to ensure quality. While compliance is important, the core reason for objective evaluation is the need for empirical evidence of progress to make informed business decisions during development.

About these practice questions

Courseiva writes every SAFe-Agilist question from scratch — 315 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This SAFe-Agilist practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SAFe-Agilist exam.