PMI-RMP Risk Monitoring And Reporting Practice Question
You are managing a project with a 'high' risk profile. Stakeholders request a report that shows the 'Residual Risk' vs 'Target Risk' levels. What does this indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The gap shows the extent of required further mitigation
The gap between residual and target risk shows how much additional mitigation is required to reach the desired risk state.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The gap shows the extent of required further mitigation
Why this is correct
This comparison indicates the remaining work needed to align with risk appetite.
- ✗
The project is over budget
Why it's wrong here
This report does not show budget data.
- ✗
The project is ahead of schedule
Why it's wrong here
This report does not show schedule data.
- ✗
The project risk is fully mitigated
Why it's wrong here
If a gap exists, the risk is not fully mitigated.
About these practice questions
Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.