PMI-RMP Risk Strategy And Planning Practice Question
Which TWO inputs are required to properly tailor a risk management methodology?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Organizational Process Assets (OPAs).
Tailoring requires understanding both the environment (enterprise) and the specific project needs (context).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Organizational Process Assets (OPAs).
Why this is correct
OPAs provide the existing standards to tailor from.
- ✓
Project context, including complexity and risk profile.
Why this is correct
Context is the driver for the tailoring decisions.
- ✗
The project team's lunch schedule.
Why it's wrong here
This is irrelevant to methodology.
- ✗
The project's social media account.
Why it's wrong here
This is irrelevant to risk management.
- ✗
The office location.
Why it's wrong here
Location is minor compared to context and assets.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.