Which THREE criteria are used to perform a 'Risk Data Quality Assessment'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Reliability of the data

Data quality is assessed based on understanding, accuracy, and reliability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reliability of the data

    Why this is correct

    Can we trust the data source?

  • Accuracy of the data

    Why this is correct

    Is the data correct?

  • Extent of the data's understanding

    Why this is correct

    Do we know what the data means?

  • Total volume of data

    Why it's wrong here

    Volume is not quality.

  • Color of the spreadsheet cells

    Why it's wrong here

    Totally irrelevant.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.