PMI-RMP Risk Strategy And Planning Practice Question
Which THREE activities are part of the 'Plan Risk Management' process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Assigning roles and responsibilities for risk.
Planning involves defining how the risk process will work, creating the plan document, and establishing the overall framework.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Assigning roles and responsibilities for risk.
Why this is correct
Role assignment is a planning task.
- ✗
Executing the project work.
Why it's wrong here
This is part of Direct and Manage Project Work.
- ✓
Defining the risk methodology.
Why this is correct
Methodology definition is a core output.
- ✗
Closing the project.
Why it's wrong here
This is part of Closing.
- ✓
Developing the Risk Management Plan document.
Why this is correct
The plan is the primary output of the process.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.