Which of the following is the best definition of 'Residual Risk'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The risk remaining after all response strategies have been implemented

Residual risk is the risk that remains after mitigation measures have been implemented.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The risk that occurs after the primary risk is avoided

    Why it's wrong here

    This is 'Secondary Risk'.

  • The risk remaining after all response strategies have been implemented

    Why this is correct

    This is the definition of residual risk.

  • The total risk before any responses are taken

    Why it's wrong here

    This is 'Inherent Risk'.

  • The risk accepted as part of the project budget

    Why it's wrong here

    This is a management reserve, not a definition of risk.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.