Risk Process FacilitationeasyMultiple ChoiceObjective-mapped

PMI-RMP Risk Process Facilitation Practice Question

Which document is the primary output of the risk identification process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk Register

The risk register is the central document where identified risks are recorded.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk Register

    Why this is correct

    The risk register is updated throughout the project with information from risk identification.

  • Lessons Learned Register

    Why it's wrong here

    This records past experiences, not current project risks.

  • Risk Management Plan

    Why it's wrong here

    This describes how risks are managed, not the specific risks themselves.

  • Risk Report

    Why it's wrong here

    This is a summary document of overall project risk, not the initial output of identification.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.