PMI-RMP Risk Monitoring And Reporting Practice Question
When a 'Risk Trigger' occurs, what must be updated in the PMIS immediately?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Risk Status and the Issue Log
Updating the status from 'Risk' to 'Issue' ensures the problem is managed with appropriate urgency.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Scope Statement
Why it's wrong here
Scope changes are separate from risk triggers.
- ✗
The Stakeholder Register
Why it's wrong here
This is only updated if the incident changes who is involved.
- ✗
The Resource Plan
Why it's wrong here
Resource allocation may change, but the primary task is logging the issue.
- ✓
The Risk Status and the Issue Log
Why this is correct
Once a trigger occurs, the risk has manifested as an issue and must be tracked accordingly.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.