Risk Monitoring And ReportingeasyMultiple ChoiceObjective-mapped

PMI-RMP Risk Monitoring And Reporting Practice Question

When a 'Risk Trigger' occurs, what must be updated in the PMIS immediately?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Risk Status and the Issue Log

Updating the status from 'Risk' to 'Issue' ensures the problem is managed with appropriate urgency.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Scope Statement

    Why it's wrong here

    Scope changes are separate from risk triggers.

  • The Stakeholder Register

    Why it's wrong here

    This is only updated if the incident changes who is involved.

  • The Resource Plan

    Why it's wrong here

    Resource allocation may change, but the primary task is logging the issue.

  • The Risk Status and the Issue Log

    Why this is correct

    Once a trigger occurs, the risk has manifested as an issue and must be tracked accordingly.

About these practice questions

This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.