What is the purpose of a risk owner in a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To provide regular updates on the status and mitigation progress of the assigned risk.
Assigning ownership ensures that someone is responsible for monitoring and managing each risk.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To pay for any damages caused by the risk.
Why it's wrong here
The risk owner manages the risk, not necessarily the financial liability.
- ✗
To perform all tasks related to the risk.
Why it's wrong here
The owner may coordinate others rather than doing everything personally.
- ✗
To blame if the risk event occurs.
Why it's wrong here
The role is about management, not fault.
- ✓
To provide regular updates on the status and mitigation progress of the assigned risk.
Why this is correct
Ownership ensures continuity in monitoring and execution.
About these practice questions
Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.